BRUSLY — The Brusly Town Council made its final payment on the sewer lagoon project Nov. 9. The council also approved most of a payment for street repairs on Orleans Quarters, holding back part of the money until the contractor fixes several bumpy spots.

All votes were 3-0. Council members Blake Tassin and Chris Kershaw were absent.

Sewer lagoon paid off

The council approved the seventh and final pay application from Spinks Construction for $225,881.40. That closes out a Water Sector-funded overhaul that dragged on through a contractor dispute, a weight-limited bridge and a broken blower.

"No more retainage," Mayor Scot Rhodes said. "All of our punch list items are done."

Rhodes said the contractor sent in the pay application a while ago. The town held it because a blower at the plant broke and a new one had to be ordered. The town's engineer has since signed off on the work.

Most of the payment will come out of what is left in the town's American Rescue Plan Act account. About $135,000 remains in that account, according to figures given at the meeting. Rhodes said about $125,000 would come from ARPA money the town had set aside as its match for the project. The rest would come from extra money that had been budgeted for engineering.

"So it's not gonna come directly from the town coffers, if you will," Rhodes said.

The project dates to the 2023 round of the state's Water Sector program. In July 2025, the council voted 3-1 to approve a $70,000 change order after a weight-limited bridge forced the contractor to use smaller trucks and longer routes to reach the lagoon. Council member Rusty Daigle cast the lone no vote at the time, arguing the contractor had breached the contract.

The final piece of the work was a polishing reactor that officials have said should give the town 20 years of service. The town is now working to insure the new equipment. At the council's Nov. 2 committee meeting, Rhodes said engineering firm Owen & White billed about two and a half hours to estimate what it would cost to replace the polishing reactor and the cover at the pond.

"That was a huge project for the town of Brusly," Rhodes said after the vote. "We don't have to worry about a whole lot back there other than normal maintenance."

Council member Sheri Young made the motion, and council member Mike Chustz seconded.

Orleans Quarters repairs

The council also approved a $62,679.10 payment to contractor RJ Daigle for patch and overlay work on Orleans Quarters. The pay application arrived the afternoon of the meeting. Rather than wait a month, Rhodes asked the council to add it to the agenda, and members agreed.

Rhodes said the original bid was $71,808. The contractor has completed $65,978 in work so far. The town is keeping 5%, or $3,298.90, as retainage.

That retainage, and a separate $5,000 change order, won't be paid until the engineer signs off.

"We always hold some, and we're not gonna pay 'em that retainage or the five thousand until our engineer approves everything," Rhodes said.

Rhodes said public works staff and the town engineer found about six spots where the patching is bumpy or has lips that need to be fixed.

The $5,000 change order covers two drainage grates set in the street. Rhodes said the overlay around them kept shifting and would not last, and the town no longer needs them since new drains were put in across the street. The parish will bring in heavier equipment to pull the grates and set a plate over the openings. Then the contractor will come back and overlay the area so it is solid asphalt. Rhodes said the work is on the parish's schedule, but he did not have a date.

The change order and the retainage are expected to come before the council in December.

Rhodes said the overlay is coming in well under what the town budgeted for road work, and that was on purpose.

"We did that on purpose to try to cut back a little bit," he said. If the town's finances hold up through spring, he said, the remaining money could go to other road repairs around town.

Daigle made the motion to approve the payment, and Chustz seconded.

A resident's question

During public comment, Orleans Quarters Drive resident Tamara Brown told the council that crews spray-painted spots in front of homes that needed repair, including hers. She said every marked spot in the subdivision was repaired except the one in front of her house. She said she drove the whole subdivision on Oct. 30 to check.

"Mine is the only one that was spray painted that was not repaired," Brown said.

Brown also told the council that a worker parked a company truck in her driveway while crews were on her street, and that she confronted him about it. She said she had sent the town photos.

Rhodes said he looked at the photos and checked with the town's engineering firm. He said her address was not on the original drawing that went out for bid, even though it may have been painted. He said that even if workers parked at her house, they did not skip her spot on purpose, because it was not on the design.

He explained that the town's public works supervisor marks spots he thinks are bad, then the engineer reviews them and decides which ones go on the plan. Rhodes said the engineer will look at her spot before the contractor comes back. If it needs work, the town will see what it would cost to fix it while crews are already out there.

"It was not done on purpose, I promise you," Rhodes said.

Coming up in Brusly:

Veterans Day breakfast. Brusly will host its Veterans Day breakfast Wednesday, Nov. 11, at 8:30 a.m. at Brusly Town Hall. Warren LeJeune is the guest speaker. Rhodes said the event is short so veterans can get to other Veterans Day events, and all veterans are invited to eat on the town.

Christmas tree lighting. The town's Christmas tree lighting at St. James Park is Friday, Dec. 4. The lighting is set for about 6 p.m., and the market that goes with it may open around 5:30 p.m.

Full Moon Market. Rhodes said the October Full Moon Market drew more than 40 vendors. The organizer has asked for dates next year and may hold the market monthly.